ACT (RS) ABB Loco (English) (10. MAIN TRANSFORMER )

Main Transformer 

General: 25 KV, 1-phase, AC Supply is taken from OHE catenary/ contact wire through pantograph, roof equipment and VCB (DJ). The same supply is fed to charge the “ parallel induction transformer” where it is stepped down to different operating voltage. .

The tank is filled with transformer oil: 

• In order to increase the insulation strength and 
• So that the arising heat loss can be dissipated through the circulating oil 

The two parallel oil circuits with pumps and heat exchangers are provided 

A spy glass is provided in each machine room to check the oil level of transformer oil. 

There are 3 secondary winding: 

a.Convertor secondary winding/Traction winding(4 nos.) 

b.Aux. Convertor secondary windings.(1 no.) 

c.Harmonic filter secondary winding.(1 no.) 




.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.